PUC Issues Emergency Order Regarding Sunoco Pipeline L.P.; Operations of Mariner 1 East Pipeline Suspended Over Safety Concerns

Published on 3/7/2018

Filed under: Gas

HARRISBURG – The Pennsylvania Public Utility Commission (PUC) today issued an Emergency Order regarding Sunoco Pipeline L.P., also known as Energy Transfer Partners (Sunoco), to suspend operations of the Mariner East 1 Pipeline (ME1) and require additional testing and analysis on that line, in response to safety concerns regarding the integrity of that pipeline.

 

According to a Petition for an Ex Parte Emergency Order filed by the PUC’s independent Bureau of Investigation (BIE) and Enforcement, engineers from the PUC’s Pipeline Safety Division investigated reports of the formation of sinkholes near the ME1, located along Lisa Drive in West Whiteland Township, Chester County.  ME1 is an eight-inch diameter Natural Gas Liquids (NGL) pipeline, used to transport liquid propane, butane and ethane. A total of three sinkholes have been discovered near, or in the path of, ME1.  The sinkholes are also near the area where construction, including Horizontal Directional Drilling (HDD), is underway for a new pipeline, known as Mariner East 2.

Today’s Emergency Order requires the following:

  • Within 24 hours of the entry of this Order, Sunoco shall run at least one in line inspection tool through the Mariner East 1 Pipeline, inspecting the pipeline from a point at least 1 mile upstream from the Lisa Drive location to a point at least 1 mile downstream from Lisa Drive.
  • Within 12 hours of completing the inspection tool run Sunoco will suspend hazardous liquids transportation service on its Mariner East 1 pipeline for a period of time, presently estimated by BIE and Sunoco to be of 10-14 days duration (the “Study Period”), in order for Sunoco to perform the following:
    • Conduct geophysical testing and analyses (including at least the following: resistivity, seismic and gravity) in the HDD area described in the BIE Petition; and
    • Share all findings of the inspection tool run and geophysical testing with BIE/Pipeline Safety staff; and,
    • Meet and discuss the findings with BIE/Pipeline Safety staff, such discussions shall include, but not be limited to Sunoco’s addition of strain gauges to Mariner East 1 in the study area.
    • During the Study Period, Sunoco shall maintain sufficient minimum pressure in Mariner East 1 to avoid gasification of NGLs.  However, the NGLs shall not be flowing during such period.
  • Sunoco will not reinstate hazardous liquids transportation service on Mariner East 1 until the earlier of the following:
    • Completion of the inspections and testing specified in the Commission’s Order, with any corrective actions taken, or planned to be taken, to the satisfaction of BIE/Pipeline Safety coupled with BIE/Pipeline Safety’s concurrence with reinstatement of transportation service on Mariner East 1, subject to Commission review and approval.
    • If BIE/Pipeline Safety does not concur with Sunoco’s request to resume service on ME1, Sunoco may file an Answer to the BIE Petition within 3 business days following notice of BIE’s noncurrence.
    • The Petition and Answer will be assigned for expedited hearing(s) before the Office of Administrative Law Judge;
    • Sunoco may not resume hazardous liquids transportation service on Mariner East 1 without prior Commission approval.

The Pennsylvania Public Utility Commission balances the needs of consumers and utilities; ensures safe and reliable utility service at reasonable rates; protects the public interest; educates consumers to make independent and informed utility choices; furthers economic development; and fosters new technologies and competitive markets in an environmentally sound manner.

For recent news releases and video of select Commission proceedings or more information about the PUC, visit our website at www.puc.pa.gov. Follow the PUC on Twitter – @PA_PUC for all things utility. “Like” PA Public Utility Commission” on Facebook for easy access to information on electric shopping.

# # #

 

Contact:

 

Complaints

Learn how to submit a complaint with a public utility. You can also search existing formal complaints.

Get Details

Subscribe to Press Releases

Keep track of PUC news and activities with press releases delivered straight to your email inbox.

Subscribe

Need More Help?

If you can't find what you're looking for here, please contact the PA Public Utility Commission. Call us at 1-800-692-7380 or contact us online.

Document Search

Public utility documents available electronically include case dockets, public meeting orders and more.

Filing & Resources

Find utility-related reports, laws and regulations, federal filings, tariffs, procedures and more.

eFILING

Consumers, utilities and attorneys can save time by submitting documents to the PUC electronically.